Product Description: Headphone Power Test Equipment Cable Fault Pinpointer locator with accuracy <0.1M
1.
Introduction:
PCLD-904P
Digital Power Cable Fault Pin-pointer is an easy operation device used to pinpoint the fault point. It integrated the function of
acoustic
magnetic synchronization method, the step voltage method, the magnetic field strength method to make the pinpointing accuracy.
NO | NAME | INTRODUCTION |
1 | LCD | |
2 | KNOB |
Adjust the
acoustic
gain or cursor;
Adjust the magnetic gain Setting the interface |
3 | SET/POWER | Long time press: power on/off;short time press: enter or exit |
4 | MUTE | Headphone on/off |
5 | CURSE/GAIN | Adjust cursor or gain |
6 | BREATHER VALVE | |
7 | SIGNAL INPUT | Use the signal line to connect with the sensor |
8 | STRAP HOOK | Install the strap |
9 | HEADPHONE INPUT | Connect with the headphone |
10 | CHARGING PORT |
NO | NAME | INTRODUCTION |
1 | Pole | I nstall method: insert into the open hole and rotate the pole as one quarter turn |
2 | Long probe | U sed for the lawn or soft ground. Remove it and install in the screw hole in the bottom |
3 | Signal port | U se to contact with the main unit with signal line |
4 | Breather valve |
2).Terms of Shipment:
Within 10 working days after received related prepayment or L/C.
3).Payment terms:
(1)T/T 100% or 50% deposit by T/T in advance, balance amount to be paid 7 days before
delivery.
(2) By irrevocable L/C at sight, to be issued immediately against confirmed order.
(3)Payment by T/T, if order amount is less than USD 20,000.
4).Warranty:
(1)We provide 1 year warranty.
(2)If the product is defective, please notify us within 3 days of delivery.
(3)All products must be returned on their original condition, in order to qualify for a refund or exchange of goods
5.Flow chart of trading activities:
NO |
Step |
Days need |
1 |
Request for quotation |
1 day |
2 |
Making quotations |
1 day |
3 |
Offer and counter offer |
3 days |
4 |
Sending and receiving samples |
3-10 days |
5 |
Sample confirmation |
3 days |
6 |
Placing a firm order |
1 day |
7 |
Paying and receiving the down payment |
1-4 day |
8 |
Factory production & Quality inspection |
15-20 days |
9 |
Paying and receiving the balance |
4 days |
10 |
Delivery of goods |
1 days |
8.Contact